MILLWOOD AVE RELOCATION

PROJECT SUMMARY

This project featured the design of a continuous right turn lane, merge areas, and new intersection at University Boulevard, impacting a four-lane divided local road, turn lanes, tapers, and internal campus roads. The relocation of traffic has improved traffic in one of the busiest intersections in Winchester.

LOCATION

Winchester, VA

CATEGORY

Institutional

Engineering Tasks

  • Public Improvement Plan for Millwood Avenue Right Turn Lane
  • Intersection Design and Roadway Design for University Boulevard
  • Striping and Signage Plan
  • Stormwater Collection Design
  • Localized Stormwater Quality Design
  • Coordination of final design with owner landscape architect and campus master landscape plan
  • Dry Utility relocation and design coordination
  • Bid Period and Construction Administration Support
  • Punch List/asbuilt review and certification

Planning Tasks

  • Represent client in traffic impact analysis, city public process meetings, and VDOT negotiations

Surveying Tasks

  • Data Acquisition for civil design (asbuilt and topography)
  • Utility location
  • Plats for Recordation
  • Easement Plats
  • Road Construction Stakeout
  • Set Property Corners