Project Description

MILLWOOD AVE RELOCATION

PROJECT SUMMARY

This project featured the abandonment of approximately 840 LF of existing Millwood Avenue and the relocation of traffic through the project area. Relocation included the design of a 900 linear foot continuous right turn lane and merge area. This project also included the design of a new intersection for University Boulevard, 500 linear feet of 4 lane divided local road and associated turn lanes and tapers, and internal university campus road alignments to meet the new design.

CLIENT

Shenandoah University
Winchester, Virginia

CONTACT

Barry Schnoor, Physical Plant Director
540.336.6687

Engineering Tasks

  • Public Improvement Plan for Millwood Avenue Right Turn Lane
  • Intersection Design and Roadway Design for University Boulevard
  • Striping and Signage Plan
  • Stormwater Collection Design
  • Localized Stormwater Quality Design
  • Coordination of final design with owner landscape architect and campus master landscape plan
  • Dry Utility relocation and design coordination
  • Bid Period and Construction Administration Support
  • Punch List/asbuilt review and certification

Planning Tasks

  • Representative for Client for development of conceptual design and management of traffic impact analysis work
  • Representative for Client for project design coordination and meetings with city staff and decision makers
  • Representative for Client for public process meetings and approvals
  • Representative for Client for VDOT and off-site property owner negotiations to acquire right of way for project

Surveying Tasks

  • Data Acquisition for civil design (asbuilt and topography)
  • Utility location
  • Plats for Recordation
  • Easement Plats
  • Road Construction Stakeout
  • Set Property Corners